After a period of tendering, audits and meetings that started in December 2017, Sagro has signed the contract for onshore decommissioning of the Tyra Redevelopment phase 4 jackets with offshore heavy lift and pipeline installation contractor Allseas.
Project highlights
Client
Allseas
Tonnage
11000 ton
Special detail
Worked at height with rope access specialists
Location
North Sea (Denmark)
Scope of work
The scope of work consists of the cleaning, demolition, recycling and disposal of 4 jackets with a combined weight of more than 10,000 tonnes and is part of Total E&P Denmark’s Tyra Redevelopment Project.
Allseas’ heavy lift vessel “Pioneering Spirit” lifted and transported the structures from the Tyra field (Denmark) to Sagro’s facilities.